How often does a scaffold need inspecting? The 30-day rule
Most Australian WHS guidance expects a scaffold to be inspected before first use, after anything that could affect it, and then on a recurring schedule once it's up — commonly every 30 days. Here's what that actually requires, and why a paper scaftag is the weakest link.
This page is general information only, based on publicly available sources as at the date this page was last reviewed (see the sources listed further down this page for that date). It is not legal, compliance, or insurance advice, is not exhaustive, and may not reflect the most current requirements -- regulations, licensing rules, and insurance thresholds change, and requirements can vary by project, site, and contract. Always verify current requirements directly with the relevant state or territory regulator, your insurer, or a qualified advisor before relying on anything here.
The short answer
SafeWork NSW requires a scaffold to be inspected at least every 30 days by a competent person, on top of a daily visual check before anyone uses it. The 30-day interval shows up consistently across state regulators' own guidance (Queensland's scaffolding code of practice and WorkSafe WA's inspection checklist both use the same figure), but exactly how it's worded, and what counts as a "competent person," varies by state.
Scaffolding licensing and inspection requirements differ by state and by the type of scaffold involved — treat this as a starting point, not a final answer for your situation, and confirm the current position with your own state or territory WHS regulator before relying on it.
What counts as a scaffold inspection
A documented check against the scaffold's current condition — base, ties, bracing, platforms, edge protection, tag status — carried out by someone qualified to judge it, not just a visual walk-by from whoever's on site that day. SafeWork NSW requires written confirmation from a competent person (a handover certificate) before a scaffold is used at all, and separately requires that the scaffold itself only be erected, altered, or dismantled by someone holding the relevant scaffolding high-risk work licence.
Why the 30-day interval exists
Scaffolds degrade through weather exposure, nearby work, and incremental modification — a board removed for access and never replaced, a tie loosened during other trade work. A fixed recurring check catches that drift between the big, obvious triggers rather than relying on someone noticing. If an inspection does turn up a safety risk, the scaffold has to be repaired and re-inspected before it's used again — a specific, penalty-backed stop-work requirement, not a paperwork formality.
Where this breaks down on paper
A scaftag hanging on the scaffold is only as good as whoever remembers to update it, and it tells a site visitor nothing a builder's office can see without physically walking the site. If the last inspection lapses past 30 days, there's often no central signal until an auditor, a principal contractor, or a regulator asks for records.
What ComplySite tracks instead
Each scaffold is logged as its own recurring item against the subcontractor responsible for it, inspected every 30 days by default (adjustable per company). An overdue inspection shows up on the dashboard the same way an expired licence does — not just on the tag at the gate — and every inspection's full history, not just the latest one, stays available for an audit-ready export. A subcontractor can log an inspection from their phone on site through the same no-login link used for document uploads, even without signal — it syncs automatically once they're back online.
Check the current position directly
- Safe Work Australia
National WHS policy body and the model Work Health and Safety Act 2011
- SafeWork NSW — Scaffolding
Source for the 30-day inspection interval and competent-person confirmation requirement — example state regulator, confirm with your own state's
This page was last reviewed against those sources on 12 November 2026. See the full sources list for every state and territory regulator.
Frequently asked questions
Does every scaffold need a 30-day inspection, or just tall ones?
The 30-day interval is generally tied to scaffolds that are incomplete or remain in use for a meaningful period, not light-duty trestles up for an hour. State guidance varies on the exact threshold, so check your own state regulator's definition rather than assuming it never applies to a smaller job.
Who's allowed to inspect a scaffold?
SafeWork NSW requires written confirmation from a competent person before a scaffold can be used, and the scaffold itself may only be erected, altered or dismantled by someone holding the relevant scaffolding high-risk work licence. A builder shouldn't assume any tradesperson on site is qualified to sign off an inspection.
What happens if an inspection lapses?
A scaffold found to have a safety risk must be repaired and re-inspected before it's used again -- this is a stop-work trigger under WHS law, with a specific penalty for failing to do so, not just a paperwork formality to tidy up later.
Does ComplySite replace the physical scaffold tag?
No. ComplySite tracks the inspection record and schedule digitally alongside whatever physical tagging the site already uses -- the point isn't to remove the tag, it's to make sure an overdue inspection is visible to the office, not just to whoever happens to walk past the scaffold.
Can a subcontractor log an inspection without a ComplySite account?
Yes. The same no-login link used for document uploads also covers logging a scaffold inspection, straight from a phone on site -- including when there's no signal, with the entry syncing automatically once the connection comes back.